Grosvenor Park III

North Bethesda / MD

Closed-Loop HVAC Hydronic , Condominium , MD

Units : 414
Stories : 17
Built : 1964
Duration : 15 months
Problem : Age-related corrosion in the hydronic piping system
Solution : Turnkey replacement of hydronic piping & isolation valves

Grosvenor Park III

Closed-Loop HVAC Hydronic , Condominium , MD
Units : 414
Stories : 17
Built : 1964
Duration : 15 months
Problem : Age-related corrosion in the hydronic piping system
Solution : Turnkey replacement of hydronic piping & isolation valves

Heating / Cooling Riser Piping

Prior to hiring SageWater, this North Bethesda high-rise condominium community was experiencing substantial age-related corrosion in the piping of its 52 closed-loop HVAC risers.  Frequent leaks in these risers were causing the property to replace them one at a time, and they ultimately decided it was more efficient and cost effective to replace all the failing risers in one project.  SageWater was hired to perform this repipe, working diligently with building management to develop a complete resident communications program (including a project-specific website).  As a turnkey contractor, SageWater is completing all renovation components for this project including: plumbing, insulation, firestopping, drywall and paint.

I was so impressed with SageWater and the work they have done here at Grosvenor Park III. The different stages were so well orchestrated with [the entire team]. Everyone was so courteous and non-intrusive. The coordination between SageWater and [property management] letting us know when each stage was going to be performed was like clockwork. Being in business for over 40 years, I know that is not an easy task! Bravo!

Anne Ryan Homeowner - Grosvenor Park III North Bethesda, MD February 12, 2016