Multifamily Apartments
Durham | NC

Mission University Pines

Like many other garden-style apartment communities built in the 1980’s-1990’s, Mission University Pines suffered from defective polybutylene piping, often causing unwanted leaks in resident’s homes. SageWater was hired to perform our turnkey service, replacing the faulty polybutylene pipes with more corrosion-resistant ones and reinstalling the affected drywall and paint. Most units were completed in 3 to 4 days in total, without residents having to move out during the process.

Units
362
Stories
3
Built
1989
Duration
4 months
Problem
Faulty polybutylene piping
Solution
Turnkey Pipe Replacement
PROPERTY STYLE
PROJECT TYPE
Testimonials
quote

SageWater came highly recommended, so we chose them to complete our project. Overall, the project went great and was completed ahead of schedule. I was particularly impressed by how well all the crew members worked together as a team. Overall, they did an excellent job!

Ray Stewart
Vice President of Maintenance Services
Mission University Pines