Multifamily Apartments
Huntsville | AL

Emerald Ridge Apartments

Shortly after Emerald Ridge Apartments was built, it began experiencing recurring leaks caused by a construction defect in the original Nibco PEX domestic water piping. The owner chose SageWater to carry out the pipe replacement based on our expertise, proven track record, and robust resident communication. We replaced the defective pipe with a product known for its reliability and durability, completing the project on time and on-budget. The client valued our turnkey process, in particular that our integrated approach kept them from needing to coordinate with multiple contractors. In the end, they credited the project with not only saving them repair costs but also with preserving resident trust and their reputation by addressing the piping problem efficiently and with minimal disruption.

Units
340
Stories
3
Built
2008
Duration
5.5 months
Problem
Construction Defect in Nibco PEX Supply System
Solution
Turnkey Pipe Replacement
PROPERTY STYLE
PROJECT TYPE
Testimonials
quote

I have nothing but good things to say about the experience.

Patrick Kennedy
President
Sealy Management Company
Other Case Studies