Multifamily Apartments
Seattle | WA

Andorra at Lake Ballinger

Plagued with corroding galvanized steel plumbing, the Andorra community experienced multiple leaks that caused huge headaches for residents and the community staff. SageWater replaced the piping throughout the property, which included intra-buildings mains and installing new pipe chases. SageWater completed the project on time and on budget and with minimal disruption to the residents. As a result, the building owner hired SageWater to provide our turnkey solution for another 1,500 units.

Units
180
Stories
4
Built
1969
Duration
2.5 months
Problem
Potable drinking water piping problems
Solution
Turnkey Pipe Replacement
PROPERTY STYLE
PROJECT TYPE