Franklin Towers | SageWater

Franklin Towers

Honolulu / HI

HI , Drain, Waste & Vent , Condominium/Co-Op , HI , Mid/High-Rise

Units : 156
Stories : 40
Built : 1982
Duration : 10 months
Problem : Failing cast iron drain, waste, and vent piping
Solution : Turnkey Pipe Replacement
Franklin Towers Condo high-rise in Honolulu, Hawaii

Franklin Towers


Units : 156
Stories : 40
Built : 1982
Duration : 10 months
Problem : Failing cast iron drain, waste, and vent piping
Solution : Turnkey Pipe Replacement

SageWater successfully completed a full-scale drain, waste, and vent (DWV) plumbing upgrade, replacing all vertical and lateral cast-iron piping in 156 units of the Franklin Towers Condominiums. We even added additional isolation valves for the individual units which gave them the capability to shut off a single unit as opposed to a stack.

At the time of the project, the roof of the building was still relatively new and under warranty but we needed to remove and replace the cast iron through-roof vent piping which would impact the roof. So, we coordinated with a roofing contractor to come out once plumbing was done so they could make repairs ensuring the building warranty remained intact. Despite this added hurdle, SageWater restored Franklin Towers to pre-construction conditions, completing the complex 40-story building project on time and under budget.

[SageWater's] quality of work was super complete, neat and tidy. Workers were kind, considerate, respectful and helpful. Very Impressed with your work. Glad we went with SageWater! Thank you!

Pamela Mew
Resident
Franklin Towers
See More Case Studies