Condos
Honolulu | HI

Yacht Harbor Towers

In this high rise, SageWater replaced deteriorated drain waste and vent piping in two buildings with 40 floors each, spanning a base with commercial properties. We installed SUDS relief piping and cored concrete in 18 stacks. This work also included the removal and re-setting of bathroom fixtures and vanities.

Units
458
Stories
40
Built
1973
Duration
27 months
Problem
Corroded DWV piping
Solution
Turnkey Pipe Replacement
PROPERTY STYLE
PROJECT TYPE
Testimonials
quote

SageWater did an excellent job repiping our unit. All the workers were professional and knew what they were doing. They alerted us when they were coming into our unit and completed the job efficiently.

Marion K., Resident
Yacht Harbor Towers