Parkland Gardens

Honolulu / HI

Drain, Waste and Vent Piping , Condominium , HI

Units : 96
Stories : 15
Built : 1976
Duration : 4 months
Problem : Severely corroded drain, waste, and vent piping
Solution : Pipe replacement, removal/resetting of bathroom vanities, light fixtures, mirrors, and toilets
Units : 96
Stories : 15
Built : 1976
Duration : 4 months
Problem : Severely corroded drain, waste, and vent piping
Solution : Pipe replacement, removal/resetting of bathroom vanities, light fixtures, mirrors, and toilets

Corroded Cast-Iron DWV Replacement

In this high rise, SageWater replaced deteriorated DWV piping, work that required removal and re-installation of bathroom vanities, light fixtures, mirrors, and toilets. SageWater finished the work on time and under budget, and exceeded the expectations of the construction manager, resident manager, and residents. Resident manager Edward Chojnowksi praised our work: “SageWater’s superb performance at Parkland Gardens was top-notch and most commendable.”