Park at Dash Point

Federal Way / WA

Polybutylene - Interior Supply , Supply Piping , Apartment , WA

Units : 182
Stories : 3
Built : 1995
Duration : 3.5 months
Problem : Faulty polybutylene piping
Solution : Turnkey piping replacement, asbestos abatement, replacing polybutylene with CPVC
Units : 182
Stories : 3
Built : 1995
Duration : 3.5 months
Problem : Faulty polybutylene piping
Solution : Turnkey piping replacement, asbestos abatement, replacing polybutylene with CPVC

Failing Polybutylene Piping

This property was one of many suffering from a failing polybutylene piping system. The management called in SageWater to provide our One Call Repipe solution, a turnkey piping replacement including asbestos abatement and replacing polybutylene with CPVC in 182 of the property’s 276 total units throughout the community. The remaining units were previously repiped. We completed the work in 3.5 months with little effect on tenants, came in under budget, and finished on time.