1717 Ala Wai

Honolulu / Hawaii

HI , Drain, Waste & Vent , Condominium/Co-Op , Mid/High-Rise

Units : 283
Stories : 31
Built : 1970
Duration : 10 months
Problem : Severely corroded and leaking cast iron waste, vent and roof drain piping​
Solution : Turnkey Pipe Replacement with asbestos abatement​

1717 Ala Wai


Units : 283
Stories : 31
Built : 1970
Duration : 10 months
Problem : Severely corroded and leaking cast iron waste, vent and roof drain piping​
Solution : Turnkey Pipe Replacement with asbestos abatement​

This project entailed the removal and resetting of entire bathrooms (including tile, marble, vanities and toilets) as well as asbestos remediation in every unit. SageWater came in under budget and completed the project two months ahead of schedule.

The scope of work presented to SageWater was daunting to say the least. SageWater staff held numerous town hall meetings to inform our owners about what to expect leading up to the project. The bottom line is that SageWater reached “substantial completion” of the scope of work two months ahead of schedule and below the initial budget.​​

Shannon Noda-Carroll